Probes to the Moon and Mars: of 8 promised launches, 3 went on time, two Chinese ones and the UAE’s
- Chang’e 4 by 2018on time
- China: to Mars by 2020on time
- UAE: at Mars by 2021on time
- Chandrayaan-3 by Aug 20220.9 years late
- Korea: Moon orbiter by 20201.6 years late
- Luna 25 by October 20211.8 years late
- Chang’e 5 by 20172.9 years late
- Europe: Mars rover by 2022not yet
Of 8 promised launches, 3 went on time, two Chinese ones and the UAE’s.
Chang’e 5, sent for lunar soil, left 2.9 years after the deadline, Luna 25 1.8 years after. Europe’s Mars rover, promised for 2022, is waiting for a launch in 2028.
More
A probe to the Moon or Mars must make its launch window: to Mars it opens every two years or so, and a week late means two years late. Here are eight promised launches of six countries and Europe.
A row is one promise: who, what and by when. The question is whether at least half came true. Answer Yes or No, or just open the answer: each row gets its outcome and what actually came of it, the card a stamp counting those that came true. Quotes and links to the facts are below.
- Europe: Mars rover by 2022 — European Space Agency (ESA), 2020 years past the deadline
promised by 2022; not happened by 11 October 2026. The rover was not launched in 2022; ESA plans a 2028 launch.
- Chang’e 5 by 2017 — Government of China (State Council white paper), 2016 years past the deadline
promised by 2017; happened 23 November 2020 (2.9 years late). Chang'e-5 launched on 23 November 2020 and returned samples in December.
GCAT — General Catalog of Artificial Space Objects (J. McDowell, planet4589.org), журнал запусков
- Luna 25 by October 2021 — Dmitry Rogozin, 2021 years past the deadline
promised by 2021; happened 10 August 2023 (1.8 years late). Luna-25 launched on 11 August 2023 Moscow time (10 August UTC).
GCAT — General Catalog of Artificial Space Objects (J. McDowell, planet4589.org), журнал запусков
- Korea: Moon orbiter by 2020 — Ministry of Science and ICT of the Republic of Korea, 2018 years past the deadline
promised by 2020; happened 4 August 2022 (1.6 years late). The Danuri lunar orbiter launched on 4 August 2022 and entered lunar orbit at the end of December 2022.
GCAT — General Catalog of Artificial Space Objects (J. McDowell, planet4589.org), журнал запусков
- Chandrayaan-3 by Aug 2022 — Jitendra Singh, 2022 years past the deadline
promised by 2022; happened 14 July 2023 (0.9 years late). Chandrayaan-3 launched on 14 July 2023, almost a year after the named month.
GCAT — General Catalog of Artificial Space Objects (J. McDowell, planet4589.org), журнал запусков
- Chang’e 4 by 2018 — Government of China (State Council white paper), 2016 years past the deadline
promised by 2018; happened 7 December 2018 (on time). Chang'e-4 launched on 7 December 2018 and on 3 January 2019 made the first landing on the far side of the Moon.
GCAT — General Catalog of Artificial Space Objects (J. McDowell, planet4589.org), журнал запусков
- China: to Mars by 2020 — Government of China (State Council white paper), 2016 years past the deadline
promised by 2020; happened 23 July 2020 (on time). Tianwen-1 launched on 23 July 2020; the Zhurong rover landed on Mars in May 2021.
GCAT — General Catalog of Artificial Space Objects (J. McDowell, planet4589.org), журнал запусков
- UAE: at Mars by 2021 — UAE Space Agency, 2015 years past the deadline
promised by 2021; happened February 2021 (on time). Hope arrived at Mars in February 2021 and entered Mars orbit.
Promises: verbatim from the primary sources, China’s 2016 space white paper, statements of space agencies and ministers. The date of the event is from a primary source, linked on the back for each row. The delay is counted from the end of the promised period: «by 2020» from the end of 2020, «in October» from the end of October. Outcome: «came true» — the promised number reached by the deadline («about» within 5%), an event happened before the end of the year promised; «exceeded» — with room to spare; «nearly» — short by no more than 10%; «late» — reached, but after the deadline; «did not come true» — not reached; «came true, then undone» — reached, then reversed. The deadline is the end of the year named.
For the UAE probe the deadline is arrival at Mars; for the others, launch. Europe’s rover was to fly on a Russian rocket; in 2022 ESA suspended the joint mission with Roscosmos. Luna 25 crashed on the Moon after launch; only the launch date is compared here.