    Pledges to build power plants in 8 countries: by the deadline, 12% to 100% of the promise

    • China: 1,200 GW wind and solar100%
    • France: wind and solar ×297%
    • US: double renewables87%
    • India: 175 GW renewables69%
    • Kenya: 5.2 GW capacity59%
    • Ethiopia: 17 GW capacity26%
    • South Africa: 10 TWh renewables17%
    • Saudi Arabia: 3.45 GW12%

    Fact at the deadline, % of the promised number

    Did it come true?Came true: 1 of 8

    By the deadline, 12% to 100% of the promise.

    China: 1,200 GW wind and solar100%France: wind and solar ×297%US: double renewables87%India: 175 GW renewables69%Kenya: 5.2 GW capacity59%Ethiopia: 17 GW capacity26%South Africa: 10 TWh renewables17%Saudi Arabia: 3.45 GW12%

    Only China reached its goal: 1,206 GW of wind and solar against 1,200, six years ahead of the deadline. Saudi Arabia built 413 MW of a promised 3,450 by 2020.

    Source: Quotes from primary sources, facts from official statistics (links on the back)Open on the chart →
    More

    Presidents and governments promised how many new power plants they would build, or how much electricity wind and sun would give, by a deadline. Here is one such pledge per country beside what came out.

    A row is one promise: who, what and by when. The question is whether at least half came true. Answer Yes or No, or just open the answer: each row gets its outcome and what actually came of it, the card a stamp counting those that came true. Quotes and links to the facts are below.

    Pledges: speeches, national development plans and programmes (document texts). Fact: China’s National Energy Administration, Eurostat, the US Energy Information Administration, India’s Ministry of New and Renewable Energy, the Government of Kenya, the US Department of Commerce, Ember and the International Renewable Energy Agency. Outcome: «came true» — the promised number reached by the deadline («about» within 5%), an event happened before the end of the year promised; «exceeded» — with room to spare; «nearly» — short by no more than 10%; «late» — reached, but after the deadline; «did not come true» — not reached; «came true, then undone» — reached, then reversed. The deadline is the end of the year named.

    The units differ: some pledges are plant capacity, others output in a year; Kenya and Ethiopia count all power plants. China reached its goal in July 2024; the deadline is 2030. France: the pledge names no starting point, the end of 2016 is taken; from the end of 2017 the growth is 1.77-fold. US: the speech did not say what to double; here it is output without hydro; wind and solar together did double. India counts without large hydro. Kenya itself lowered the goal to 4,192 MW and missed that too. Ethiopia: 4,500 MW is a rounded estimate; the big dam only came online in 2022–2025. South Africa’s goal is broader than electricity (solar water heaters, biofuels); electricity output is taken for comparison, including hydro that already worked.

    A question for this picture

    Why do some countries build plants faster than promised and others several times slower?